September 24, 2026

Understanding Current FCC Pole Attachment Rules and How They Relate to One-Touch Make-Ready

 

Broadband expansion depends on one critical resource that most people never think about: utility poles. These wooden structures carry power lines, cable TV, telephone wires, and fiber optic cables. When a telecommunications provider wants to add new fiber to a pole, it must navigate a complex process governed by federal regulations.

The Federal Communications Commission (FCC) sets the rules for pole attachments under Section 224 of the Communications Act. These rules determine how quickly broadband providers can access utility poles and how much they pay for that access. For contractors, engineers, and project managers working in telecom infrastructure, understanding these regulations is essential to keeping projects on schedule and within budget.

Recent updates to FCC pole attachment rules took effect on May 7, 2026, bringing significant changes to timelines and processes. These changes directly impact how One-Touch Make-Ready works in practice and create new opportunities for faster broadband deployment.

What Are FCC Pole Attachment Rules?

FCC pole attachment rules establish the framework for how telecommunications companies access utility poles owned by electric utilities and other pole owners. The rules cover everything from application procedures to pricing formulas to dispute resolution.

Under Section 224 of the Communications Act, the FCC has authority to regulate pole attachments to ensure that broadband providers have fair and reasonable access to utility infrastructure. This matters because approximately 70% of broadband networks in the United States rely on aerial construction using existing utility poles.

The core principle behind these regulations is simple: pole owners cannot unreasonably deny access or charge excessive fees. However, the practical application involves detailed timelines, notification requirements, and technical standards that govern every step of the attachment process.

Key Timeline Requirements Under Current Rules

The FCC's Fifth Report and Order, adopted in July 2025, established specific deadlines for each phase of the pole attachment process:

  • Application review: Utilities have 10 business days to determine if an application is complete
  • Survey completion: 45 days for standard orders; 90 days for large orders (over 300 poles)
  • Make-ready estimates: 14 days after survey completion for standard orders; 29 days for large orders
  • Make-ready work: 30 days in the communications space; 90 days in the power space for standard orders
  • Large order make-ready: 120 days in communications space; 180 days in power space

Federal rules now impose firmer timelines on the pole attachment process. The FCC's July 2025 order established a timeline for large pole attachment requests, accelerated contractor approval, and adopted measures to foster collaboration between utilities and attachers. Whether those changes will meaningfully speed deployment is not yet established. 

The Congressional Research Service notes that some states have reported timelines running up to five years in total for pole survey results and make-ready completion, and concludes that the effect of pole attachment issues on federally funded build-out deadlines remains to be seen. Regulatory fragmentation compounds the difficulty, with 23 states and the District of Columbia administering their own pole attachment rules rather than deferring to the FCC.

The Make-Ready Challenge

Make-ready work refers to the modifications needed on a utility pole before a new attachment can be installed. This might include moving existing cables, replacing hardware, or even replacing the entire pole if it cannot support additional load.

The traditional make-ready process creates a major bottleneck in broadband deployment. Here is why: each existing attacher on a pole must move its own equipment before the new attacher can install fiber. If a pole has cables from an electric utility, a telephone company, and a cable TV provider, each entity must schedule and complete its own work in sequence.

This sequential approach leads to significant delays. Industry data shows that make-ready timelines can stretch from 135 to 225 days before construction crews can install a single strand of fiber. The costs add up quickly too. Simple rearrangements typically cost $380 to $900 per pole, while complex work involving multiple parties can reach $2,100 per pole or more. Pole replacements can cost $3,400 to $6,500 per pole.

For a project involving hundreds or thousands of poles, these delays and costs can derail deployment schedules and strain budgets.

How One-Touch Make-Ready Changes the Game

One-Touch Make-Ready (OTMR) offers a solution to the sequential make-ready problem. Under OTMR, a single qualified contractor can perform all necessary rearrangement work in one coordinated visit, rather than waiting for each existing attacher to complete its portion separately.

The FCC adopted OTMR rules in 2018 for "simple make-ready" work in the communications space. Simple make-ready includes routine tasks like moving cables or adjusting attachment heights that do not require specialized skills or create safety concerns.

How OTMR Works in Practice

  1. Application submission: The broadband provider applies to attach to the pole
  2. Eligibility determination: The pole owner reviews the request and determines if OTMR applies
  3. Advance notice: The new attacher provides notice to the pole owner and existing attachers
  4. Single-crew execution: A qualified contractor performs all rearrangements in one mobilization
  5. New attachment installation: The fiber or communications equipment is installed

OTMR can compress make-ready timelines by 30 to 60 days on eligible projects. This acceleration is critical for meeting deployment deadlines, especially for projects funded through programs like the Broadband Equity, Access, and Deployment (BEAD) Program.

The 2026 FCC rule updates expanded self-help and OTMR rights for broadband builders. Utilities must now notify attachers within 15 days if they cannot meet survey or make-ready deadlines. This early warning allows attachers to invoke self-help remedies, including using their own qualified contractors to complete the work.

Connecting Pole Attachment Rules to OTMR Success

Understanding how FCC pole attachment rules relate to OTMR is essential for maximizing deployment efficiency. The regulations work together in several important ways.

Contractor Approval Timelines

The 2026 rules require utilities to respond within 30 days to requests from broadband providers seeking approval for new contractors to perform survey, estimate, and make-ready work. Previously, contractor approval could take months, creating a hidden bottleneck before OTMR could even begin.

Large Order Provisions

For large attachment requests (over 300 poles), the FCC created new advance notice and coordination requirements. Attachers must provide 15 days advance notice for mid-size orders (300 to 3,000 poles) and 30 days for very large orders (over 3,000 poles). These provisions help utilities plan resources while maintaining predictable timelines.

Restrictions on Utility Delays

The FCC prohibited utility-imposed limits that effectively cap how many pole attachments an attacher may seek in a given period. This prevents utilities from artificially slowing large-scale deployments by limiting application volume.

BEAD Program Compliance

Cooperatives and municipal utilities participating in the BEAD Program as subgrantees must now comply with FCC pole attachment rules as a condition of accepting funding. This extends federal protections to attachers working with entities that were previously exempt from Section 224 requirements.

Practical Implications for Telecom Infrastructure Projects

For organizations involved in broadband deployment, these regulatory changes create both opportunities and responsibilities.

Planning and Engineering

  • Accurate make-ready assessments are more important than ever. With tighter timelines, there is less room for surprises during construction. Comprehensive pole loading analysis and field surveys help identify potential issues before they cause delays.

Contractor Qualifications

  • OTMR eligibility depends on using qualified contractors approved by the pole owner. Organizations should maintain relationships with approved contractors and understand the approval process for new contractors in each utility territory.

Documentation and Compliance

  • The new rules include specific notification requirements and deadlines. Missing a deadline can forfeit self-help rights or trigger disputes. Robust project management systems help track applications, notices, and responses across large deployments.

Cost Management

  • Understanding make-ready cost allocation is critical for accurate budgeting. The FCC has clarified that new attachers cannot be forced to pay for pre-existing safety violations on poles. This ruling, issued in early 2026, protects attachers from bearing costs that should fall on pole owners.

Looking Ahead

The FCC continues to consider additional pole attachment reforms. A Fourth Further Notice of Proposed Rulemaking, released alongside the 2025 order, seeks comment on expanding OTMR to complex work and other streamlining measures. 

While no timeline exists for final action, the direction is clear: regulators want to remove barriers to broadband deployment. For telecom infrastructure professionals, staying current on these regulations is not optional. The rules directly impact project timelines, costs, and feasibility. Organizations that understand and leverage the regulatory framework will have a competitive advantage in winning and executing broadband projects.

Navigating FCC pole attachment rules and OTMR requirements takes specialized knowledge and experience. From OSP engineering and make-ready assessments to aerial construction and fiber splicing, having the right partner makes the difference between a project that stays on schedule and one that stalls in regulatory limbo.

Celerity Integrated Services brings decades of experience in telecommunications infrastructure, serving carriers, utilities, and organizations across the full project lifecycle. Whether you need engineering support for pole applications, One-Touch Make-Ready construction services, or ongoing maintenance, Celerity has the expertise to keep your project moving.

Ready to discuss your next broadband deployment? Contact Celerity to learn how our team can help you navigate pole attachment requirements and accelerate your timeline.

—Frequently Asked Questions

What are FCC pole attachment rules?

  • FCC pole attachment rules are federal regulations under Section 224 of the Communications Act that govern how telecommunications companies access utility poles. These rules establish timelines for application review, surveys, make-ready work, and pricing. They ensure broadband providers have fair and reasonable access to pole infrastructure for deploying fiber and other communications networks.

What is One-Touch Make-Ready?

  • One-Touch Make-Ready (OTMR) is a pole attachment process that allows a single qualified contractor to perform all necessary rearrangement work on a utility pole in one visit. Instead of waiting for each existing attacher to move its equipment separately, OTMR consolidates the work, reducing make-ready timelines by 30 to 60 days on eligible projects.

How long does the pole attachment process take under current FCC rules?

  • Under the FCC's 2026 rules, standard pole attachment requests follow a 148-day framework from application to construction authorization. This includes 10 business days for application review, 45 days for surveys, 14 days for estimates, and 30 to 90 days for make-ready work depending on the space involved. Large orders have extended timelines of up to 90 days for surveys and 120 to 180 days for make-ready.

What services does Celerity provide for pole attachment projects?

  • Celerity Integrated Services provides comprehensive telecommunications infrastructure services including OSP engineering, make-ready assessments, pole application processing, aerial and underground construction, fiber splicing and testing, and One-Touch Make-Ready construction. The company serves telecommunications carriers, electric utilities, and organizations throughout all project phases from planning through maintenance.

How do the 2026 FCC pole attachment rules affect BEAD-funded projects?

  • The 2026 rules extend FCC pole attachment protections to cooperatives and municipal utilities participating in the BEAD Program as subgrantees. This means BEAD-funded projects benefit from federal timeline requirements and self-help remedies, even when working with pole owners that were previously exempt from Section 224 regulations.

What is make-ready work and why does it cause delays?

  • Make-ready work includes any modifications needed on a utility pole before a new attachment can be installed, such as moving existing cables, replacing hardware, or replacing poles. Delays occur because traditional processes require each existing attacher to complete its work sequentially. Industry data shows make-ready can take 9 to 16 months, with some projects experiencing delays of up to five years.

June 17, 2026

How to Connect Multi-Campus University Systems with Smart OSP Engineering

Universities don't run on good intentions. They run on bandwidth. Every lecture hall streaming video. Every research lab transferring massive datasets. Every residence hall full of students who expect instant connectivity. When a campus spans multiple locations (sometimes miles apart) the fiber network connecting them isn't just infrastructure. It's the backbone of its operations.

Connecting multi-campus systems is nothing like wiring a single building. The challenges multiply. The stakes get higher. And the margin for error shrinks to almost nothing. These challenges are what many facilities teams discover too late in the planning process.

So how does a university get it right? It starts with understanding what makes university OSP (Outside Plant) engineering fundamentally different, and what questions to ask before actual work begins. The fiber optic market is growing at a compound annual growth rate of 16.64% through 2034, according to industry analysts. Universities are racing to keep pace with bandwidth demands that seem to double every few years. But rushing a multi-campus buildout without proper OSP engineering creates problems that last decades.

Why Multi-Campus Fiber Networks Are Different

A single-campus network has one set of stakeholders, one terrain profile, and one construction timeline to manage. Multi-campus systems multiply every variable. They deal with different soil conditions at each location. Different building ages and entry point challenges. Different departmental priorities competing for attention. And often, different local permitting requirements depending on where each campus sits.

In our work with higher education clients, we've seen institutions inherit networks designed 15 years ago that can't support today's computing needs. The original engineers didn't plan for growth. They didn't build in redundancy. And now, retrofitting costs three times what doing it with all these variables taken into account would have cost originally.

The 5 Biggest OSP Challenges Universities Face

1. Terrain That Doesn't Cooperate

Every campus has obstacles such as historic quads, mature tree canopies, and underground utilities from decades ago that don't show up on satellite imagery. Rocky terrain is particularly challenging. One project we supported involved a campus built on Pennsylvania bedrock. Standard trenching wasn't an option. The engineering team had to design around geological surveys, using directional boring and strategic aerial segments to complete the backbone.

2. Academic Calendar Constraints

Campus construction schedules need to align with the academic calendar. Contractors cannot disrupt the main walkways during move-in weekend or operate heavy equipment near the library, for example, during finals. On university campuses, workable construction windows are often measured in weeks rather than months.

Effective OSP planning integrates the academic calendar into the project timeline from the start. Teams phase work during summer breaks, coordinate around major campus events, and prepare contingency plans when weather delays threaten to extend work into the fall semester.

3. Stakeholder Complexity

A corporate campus has one decision-maker. A university has dozens. IT wants maximum bandwidth. Facilities department wants minimal disruption. The provost wants the project done before the capital campaign launch. The grounds department wants to protect the historic elm trees. And everyone has veto power over something.

Successful multi-campus projects require a feasibility study that gets all stakeholders aligned before design begins. Otherwise, the redesign might involve multiple rounds.

4. Future-Proofing Uncertainty

How much bandwidth will a campus need in 2035? Nobody knows for certain. But the fiber installed today needs to handle whatever comes next. A 288-count fiber backbone costs marginally more than 144-count during installation. But adding capacity later means digging up the same routes again.

5. Budget Realities

An OSP infrastructure typically represents 60-70% of total network capital expenditure. Underground installation runs $5,000 to $20,000 per mile depending on conditions. The institutions that stay on budget are the ones that invest in thorough engineering upfront. Every dollar spent on route optimization and constructability analysis saves dollars during construction.

Planning A Multi-Campus Fiber Architecture

The most resilient university networks follow a three-tier hierarchical model:

  • Core Layer: The central data center or network operations center that serves as the hub for all campus connections.
  • Distribution Layer: Major buildings on each campus that aggregate traffic from surrounding structures.
  • Access Layer: Individual buildings, labs, and facilities that connect to their nearest distribution point.

This architecture creates natural redundancy. If one distribution node fails, traffic can reroute through alternate paths. For multi-campus systems, it also allows each location to operate semi-independently during maintenance windows.

The key decision is where to place the distribution nodes. They need to be:

  • Geographically central to the buildings they serve
  • Accessible for maintenance without disrupting campus operations
  • Protected from environmental risks (flooding, construction zones)
  • Connected to at least two independent pathways back to the core

Underground vs. Aerial: Making the Right Call

Every multi-campus project faces this question: is the fiber buried, or is it strung overhead?

Underground Advantages

Underground infrastructure provides several key advantages. It remains protected from weather, vehicle damage, and vandalism. It typically delivers a longer lifespan while requiring less maintenance. Once installed, it stays visually unobtrusive and preserves the surrounding aesthetic. In many historic districts, underground placement is also required.

Underground Challenges

Underground construction also presents several challenges. It often carries higher installation costs and requires a longer project timeline. Excavation can disrupt campus operations and daily activities during construction. Installation can also become more complex in rocky terrain or in utility corridors that are already congested.

Aerial Advantages

Aerial infrastructure offers several advantages. It can be installed more quickly, typically requires lower upfront costs, and allows easier access for repairs and maintenance. It also performs well in areas where existing pole infrastructure is already in place.

Aerial Challenges

Aerial deployment also comes with challenges. Because it remains exposed, it is more vulnerable to weather-related damage. It can affect campus aesthetics, often requires pole attachment agreements, and may have a shorter lifespan in harsh climates.

Most university projects use a hybrid approach. Underground for high-visibility areas and critical backbone routes. Aerial for back-of-campus connections and temporary construction phases. The right mix depends on specific conditions. A thorough engineering assessment maps every route option before recommending the optimal combination.

Real-World Success: Lessons from Complex Buildouts

One project that illustrates these principles involved connecting three separate campus locations for a major Pennsylvania university. The scope included:

  • 288-count fiber backbone across all three sites
  • Underground installation through rocky terrain
  • Coordination with ongoing campus construction
  • Redundant pathways for failover protection

The engineering team conducted geological surveys before finalizing routes. They identified areas where bedrock made trenching impractical and designed directional boring solutions. They scheduled major excavation during summer break and used fiber splicing techniques that minimized splice points along the route.

The project was completed on budget and the difference was investing time in planning before construction began.

Getting Started: Next Steps

If you're considering a multi-campus fiber buildout, here's where to begin:

  1. Audit your existing infrastructure. What fiber is already in the ground? What condition is it in? What capacity does it have?
  2. Map your bandwidth requirements. Not just today's needs—project forward 10-15 years. Include research computing, IoT expansion, and technologies that don't exist yet.
  3. Engage stakeholders early. Get IT, facilities, administration, and academic leadership aligned on priorities before you start designing.
  4. Commission a feasibility study. A thorough engineering assessment identifies obstacles, estimates costs, and creates realistic timelines.
  5. Choose partners with university experience. Multi-campus buildouts have unique challenges. Work with teams who've solved them before.

Getting it right matters. And it starts with asking the right questions. Celerity has supported complex fiber infrastructure projects for more than 20 years, including multi-campus university systems across the Northeast. Contact our engineering team to discuss your project.

June 3, 2026

How to Build a Business Case for Campus Fiber Ownership: A Guide for University IT and Finance Leaders

A campus network supports far more than connectivity. It powers research, online learning, administrative systems, student services, and the daily digital experience across the institution. Yet many universities still lease bandwidth from carriers, paying recurring fees while outside providers control capacity, upgrade timelines, and key network decisions.

Fiber ownership offers a different path. It starts with a question IT leaders and finance teams should evaluate together: what would change if the institution owned the fiber instead?
Building that business case requires both technical and financial discipline. When universities align network requirements with long-term capital planning, they can shift from unpredictable operating expenses to a depreciable infrastructure asset designed to serve the campus for decades.


This guide walks through that framework step by step.

Why Campus Fiber Ownership Matters 

Higher education faces a perfect storm of pressures. Enrollment competition is fierce. According to the National Student Clearinghouse Research Center, fall 2025 enrollment reached 19.4 million students, but private nonprofit four-year institutions saw a 1.6% decline. Students have options. And increasingly, they're choosing institutions that deliver seamless digital experiences.

Meanwhile, bandwidth demands are exploding. AI research computing, hybrid learning platforms, IoT sensors across facilities, and hundreds of thousands of connected devices require infrastructure that can scale without carrier negotiations.

The institutions that own their fiber networks control their destiny. Those that lease? They're at the mercy of service agreements, capacity limits, and annual price increases.

Ownership vs. Leasing: Understanding the Real Trade-Offs

Let's be direct about what each model actually means.

  • Leasing bandwidth 
    • Operates primarily on operational expenditure (OpEx). You pay monthly fees for capacity. When you need more, you pay more. There's no upfront capital outlay, which appeals to institutions with constrained budgets or uncertain future demands. But here's the catch: total cost of ownership rises linearly as your network grows. Every bandwidth upgrade means another line item on next year's budget.
  • Owning dark fiber 
    • Requires substantial upfront capital investment. You're purchasing infrastructure, not renting it. But ownership delivers lower total cost of ownership at scale—particularly for institutions expecting network demands of 3x100Gbps or more. You choose your own wavelength technologies, capacity levels, and upgrade paths. No carrier dependencies. No surprise fees when you need to scale.

There's also a security dimension. Owned fiber enables private, high-security networks where traffic stays off public internet and carrier networks entirely. For research institutions handling sensitive data, this isn't a nice-to-have. It's essential. Some institutions explore Managed Optical Fiber Networks (MOFN), which blend ownership benefits with managed services. This approach works well when acquiring dark fiber poses challenges or when your team prefers delegating network operations to a provider while retaining infrastructure control.

Building A Business Case: The 5-Pillar Framework

A compelling business case speaks two languages: technical necessity and financial return. Here's the framework that works.

Pillar 1: Current State Audit

The first step is understanding what the institution is actually spending today. Finance and IT teams should review at least three years of network service invoices and document every carrier contract, bandwidth tier, recurring fee, and overage charge. They should also map the current network environment, identifying what infrastructure the university owns, what it leases, and what assets are approaching end of life.

This type of audit often uncovers meaningful opportunities. Institutions frequently find hidden costs, overlapping services, underused capacity, or legacy agreements that no longer align with current needs. Just as importantly, the audit establishes a clear financial baseline for evaluating ROI and comparing ownership against continued leasing. A thorough fiber audit can identify infrastructure gaps and document existing assets with precision.

Pillar 2: Demand Forecasting

Institutions should project bandwidth needs across the next decade rather than planning only for current demand. That forecast should account for research computing initiatives, especially AI and machine learning workloads, enrollment growth or stabilization goals, expansion of hybrid and online learning, IoT deployments across campus facilities, and connectivity requirements between multiple campuses or remote sites.

Leadership should approach these estimates with ambition rather than caution. Fiber infrastructure often remains in service for 25 to 30 years or longer, so underbuilding can create expensive limitations later. 

Many universities continue to rely on fiber installed decades ago while upgrading the electronics layered on top of it to meet modern performance needs. The most effective strategy is to build for where the institution is headed, not where it stands today.

Pillar 3: Total Cost of Ownership Analysis

This is where the business case lives or dies. Model two scenarios across 10 years:

Scenario A (Leasing): Current carrier costs, projected annual increases (typically 3-5%), capacity upgrade fees, contract renewal terms.

Scenario B (Ownership): Capital investment for fiber installation, optical equipment, operations support, ongoing maintenance, and staff requirements.

For institutions with substantial bandwidth demands, fiber ownership often reaches breakeven within five to seven years. After that point, the network can generate meaningful long-term savings across the remaining life of the infrastructure, which often extends another 18 to 23 years or more.

A thorough financial model should also account for costs that are frequently overlooked in standard comparisons. These include staff time spent managing carrier relationships and contract renewals, downtime or productivity losses caused by capacity constraints, and the opportunity cost of delayed research initiatives or postponed technology programs. Including these factors creates a far more accurate view of total value.

Pillar 4: Risk Assessment and Redundancy

Fiber ownership isn't just about cost. It's about control and resilience.

When Lehigh University needed to connect three campuses with a robust, redundant fiber network, they faced real challenges: steep terrain, rocky soil, and construction that couldn't disrupt student life. The solution? A 288-count buried fiber build (not aerial), constructed during off-hours, completed within one year and on budget. That redundancy now protects research and academic data from environmental outages.

Document the risks of not owning your infrastructure: carrier outages, contract disputes, capacity constraints during critical periods, and dependency on third-party upgrade timelines.

Pillar 5: Stakeholder Presentation

CFOs and board members evaluate decisions through financial impact, risk, and long-term institutional value rather than technical specifications alone. That means network proposals should translate bandwidth needs into clear business language.

Ownership can shift unpredictable monthly operating expenses into a depreciable capital asset with long-term utility. A single investment may provide 25 to 30 years of service life, creating a stronger return profile over time. Modern infrastructure can also strengthen competitive positioning by supporting student recruitment, retention, digital learning expectations, and campus experience. 

For research institutions, greater capacity can enable grant-funded initiatives, advanced computing programs, and revenue-generating partnerships that depend on robust connectivity.

The most effective presentation often starts with a 10-year total cost of ownership comparison, then addresses risk reduction and operational resilience, and closes by showing how the investment supports broader strategic goals.

Total Cost of Ownership: What the Numbers Actually Show

Industry data shows that organizations crossing the 3x100Gbps threshold see distinct TCO advantages with ownership versus leasing. The math shifts because leasing costs scale linearly with demand, while ownership costs remain relatively fixed after initial investment.

Consider the Decorah, Iowa, municipal fiber model: a $13.7 million investment delivering gigabit symmetrical service with full local control. The ownership model avoided public-private partnership pitfalls and created long-term infrastructure value for the community.

Universities operate on similar logic. A campus fiber network isn't a multi-decade asset. When you factor in:

  • Elimination of recurring carrier fees
  • Unlimited capacity scaling without service charges
  • Equipment ownership (no lease-end surprises)
  • Reduced vendor dependency

The ownership model often delivers 40-60% lower TCO over a 20-year horizon compared to equivalent leased capacity.

Making the Case to Your Board: Practical Next Steps

Here's your action plan.

Step 1: Commission a feasibility study that maps your current infrastructure, projects future demands, and models ownership versus leasing scenarios.

Step 2: Engage OSP engineering expertise to design a network that meets your specific campus topology, whether that's aerial construction, underground builds, or a hybrid approach.

Step 3: Build your presentation around the 5-pillar framework. Lead with financials, support with technical necessity, close with strategic vision.

Step 4: Plan for ongoing maintenance from day one. A 25-year asset requires a 25-year maintenance strategy.

In our work with educational institutions, we've seen the difference between networks built for today and networks built for tomorrow. The institutions that invest in ownership with proper planning, quality construction, and meticulous documentation position themselves for decades of competitive advantage. Contact us to discuss your campus fiber ownership project.

Contact Us

Name

1 2 … 38
footer-logo

Subscribe to our newsletter to stay Well Connected with Celerity Integrated Services, Inc.

Contact Us

3500 AM Drive,
Quakertown, PA 18951

P 215 538 1600
F 215 538 1602

info@nextmiletech.com

proview

© 2025 Celerity Integrated Services. Privacy Policy. Site by Smith & Howell Design Co.

Back to top Arrow